Book a Consultation

Energy Permitting Database – All 50 States

Comprehensive database of energy infrastructure permitting requirements across all 50 states. Find the permits you need, average approval timelines, and key agency contacts.

State-by-State Permitting Requirements

Navigate complex energy permitting requirements with our comprehensive 50-state database. Below are the top energy-producing states with key permitting information.

Top Energy States – Quick Reference

StatePrimary AgencyMajor Permits RequiredAverage Timeline
TexasTexas Commission on Environmental Quality (TCEQ)Air Quality Standard Permit, Water Quality Certification, Coastal Zone Management Consistency6-12 months
CaliforniaCalifornia Energy Commission (CEC)CEC Certification (>50 MW), CEQA Review, Air District Permit, Coastal Commission12-24 months
New YorkNY State Public Service CommissionArticle 10 Siting (>25 MW), Article VII (transmission), SEQRA Review12-18 months
FloridaFlorida Dept. of Environmental Protection (FDEP)Power Plant Siting Certification, Water Quality, Air Quality, Environmental Resource Permit9-15 months
PennsylvaniaPA Dept. of Environmental Protection (DEP)Air Quality Plan Approval, Water Obstruction/Encroachment, Chapter 105 Permit6-12 months
OhioOhio Power Siting Board (OPSB)Certificate of Environmental Compatibility, Section 401 Water Quality, Air Permit9-12 months
IllinoisIllinois Commerce Commission (ICC)Certificate of Public Convenience, Air Permit, NPDES Water Permit9-15 months
North CarolinaNC Utilities Commission (NCUC)Certificate of Public Convenience & Necessity, Air Quality, Water Quality6-12 months
ArizonaArizona Corporation Commission (ACC)Certificate of Environmental Compatibility, Air Quality, Water Rights6-9 months
ColoradoColorado Public Utilities Commission (PUC)Certificate of Public Convenience, Air Permit, Water Right9-12 months

Federal Permitting Requirements

Most energy projects require federal permits in addition to state approvals. Key federal agencies and permit types:

Permit/ApprovalAgencyApplies ToTypical Timeline
FERC CertificateFederal Energy Regulatory CommissionInterstate natural gas pipelines, LNG terminals, hydropower (>5 MW)12-24 months
NEPA Review (EA or EIS)Various (lead agency dependent)All projects on federal lands or requiring federal permits/funding6-18 months
Section 404 PermitU.S. Army Corps of EngineersProjects affecting wetlands or waters of the U.S.3-12 months
FAA Determination of No HazardFederal Aviation AdministrationWind turbines, transmission towers near airports (structures >200 ft)1-3 months
Endangered Species ConsultationU.S. Fish & Wildlife Service / NOAA FisheriesProjects in critical habitat or affecting listed species3-12 months
Coastal Zone ConsistencyState coastal program (federal NOAA oversight)Projects in coastal zones affecting coastal resources6-12 months
BLM Right-of-WayBureau of Land ManagementProjects crossing federal public lands6-18 months
Section 106 ReviewState Historic Preservation Office (SHPO)Projects potentially affecting historic/cultural resources3-6 months

Permitting by Project Type

☀️ Utility-Scale Solar (>5 MW)

Typical State Permits:

  • Power Plant Siting Certificate or equivalent (varies by state)
  • Air Quality Permit (usually minor source – minimal emissions)
  • Water Quality/Stormwater Permit (NPDES or state equivalent)
  • Land Use/Zoning Approval (county or municipal)
  • State Environmental Review (CEQA, SEQRA, NEPA-equivalent)
  • Interconnection Agreement (utility-specific, not permit but critical)

Federal Permits (if applicable):

  • BLM Right-of-Way (if on federal lands)
  • Army Corps Section 404 Permit (if affecting wetlands)
  • Endangered Species Act Consultation (if habitat present)

Average Total Timeline: 12-18 months
Key Issues: Land use compatibility, visual impacts, agricultural land conversion, interconnection queue
Fastest States: Texas (6-9 months), Arizona, Nevada
Slower States: California (18-24 months), New York, Massachusetts

💨 Wind Energy (Onshore)

Typical State Permits:

  • Power Plant Siting Certificate
  • FAA Coordination and Determination of No Hazard (federal but state coordinated)
  • Wildlife/Endangered Species Assessment and Permit
  • Noise Ordinance Compliance (local)
  • Shadow Flicker Assessment
  • Decommissioning Plan and Financial Assurance

Federal Permits:

  • FAA Form 7460-1 Determination of No Hazard (required for all turbines)
  • USFWS Eagle Take Permit (if in eagle habitat)
  • BLM Right-of-Way (if on federal lands)

Average Total Timeline: 12-24 months
Key Issues: Bird/bat mortality studies, radar interference (DOD, NEXRAD), local opposition, setback requirements (often 1,000+ ft)
Top Wind States (Streamlined): Iowa, Oklahoma, Kansas, Texas, North Dakota

⚡ Natural Gas Pipeline (Interstate)

Federal Permits (Required):

  • FERC Certificate of Public Convenience & Necessity (lead permit)
  • Army Corps Section 404 Individual Permit (waterbody crossings)
  • NEPA Environmental Impact Statement (EIS)
  • Endangered Species Act Section 7 Consultation
  • National Historic Preservation Act Section 106 Review

State Permits:

  • Water Quality Certification (Section 401 – state can veto)
  • Air Quality Permit (compressor stations)
  • Coastal Zone Management Consistency Determination
  • State-Specific Environmental Review

Average Total Timeline: 24-36 months (FERC process is lengthy)
Key Issues: Landowner opposition, eminent domain challenges, waterbody crossing restrictions, climate impact scrutiny
Recent Trend: States increasingly denying Section 401 water quality certifications on policy grounds

🔋 Energy Storage (Battery Systems)

Typical Permits:

  • Building Permit (structural, electrical, fire protection)
  • Fire Code Compliance Review (NFPA 855)
  • Electrical Permit and Interconnection Agreement
  • Zoning/Land Use Approval
  • Environmental Review (typically limited for standalone projects)
  • Stormwater Permit (if >1 acre disturbance)

Federal Permits: Usually none (unless co-located with federal project or on federal land)

Average Total Timeline: 6-12 months
Key Issues: Fire safety (thermal runaway concerns), siting near residential areas, emergency response planning
Trend: Most streamlined permitting process for energy infrastructure; many states expediting battery storage


Expert Tips for Faster Permitting

Early Agency Engagement

Contact permitting agencies during project development phase, not after design is finalized. Pre-application meetings identify issues early and reduce costly delays.

Complete Applications

Incomplete applications are the #1 cause of permitting delays. Use agency checklists meticulously and consider hiring consultants familiar with the specific regulatory process.

Community Outreach

Proactive community engagement reduces opposition and prevents delays from public comment periods or local government resistance. Host information sessions early.


Need Permitting Strategy Support?

Elkfort’s energy consulting team has guided clients through permitting processes for $2B+ in energy infrastructure projects across 25+ states.


Disclaimer: This database is compiled from publicly available information and is updated quarterly. Permitting requirements change frequently. Always verify current requirements with the relevant permitting agency before proceeding with your project. This information is for general guidance only and does not constitute legal or regulatory advice.

Last Updated: November 2025